Friday, December 19, 2008

PRE-CONSTRUCTION MEETING ACCKB PACKAGE 1

DATE : 04 DEC 2008 10.00 AM
VENUE : LEVEL 25 JKR MID VALLEY
CHAIRMAN : AR ZAHARIAH - PENGARAH BAHAGIAN KERJA KESIHATAN

MAJOR ISSUE :
1. Requirement to obtained Letter of clearance/permission/no objection from Local Authorities( MPKKB, TNB, Jabatan Air Kelantan)
2. To submit Project Quality Plan - PQP, Safety Manual, Critical Path Method, CPM, financial projection, s-curve ( financial and physical progress )
3. To coordinate the works should be done by Main contractor-MISB, Redicare, HRPZ's sub contractor.

Thursday, December 18, 2008

ACCKB- Package 1 - Letter of Award - LA - 19 Nov 2008

Menang Intan Sdn Bhd recieved LA from JKR CKUB for ACCKB Package 1.

Its mentioned :
Date of site possession 01 December 2008.
The Contract Value is RM 8.975 M
Construction Period : 8 months