Monday, July 28, 2008

NCR ISSUE

NCR ISSUE
Date of Issued : 20 May 2008
Issued by : JKR CUB

NCR is Non Compliance Report. Means the proposal is not compliance in:

1. No proposal or doesn't say - not mentioned in early proposal
2. No comply to specification and requirement.
3. Proposed material or specification which are not in approved list by JKR/KKM.
4. Not comply to EPU requirements.

The first contractor proposal, JKR and KKM list a few significant NCR issue.

1. The proposal of Decanting works for Pejabat Pengarah and relocation of New Pejabat Pengarah. (Quarters Block A)with 2 option.
a. to relocate at the ground floor of the quarters blocks instead using the upper floor units. or
b. to maintain existing Pejabat Pengarah.

2. To proposed fibre optic as the option. - confirmation will be decide when the stage of Final Negotiation with KKM, MOF and JKR.

3. Internal building layout for Respiratory Unit and Ward 6.

4. Others technical issue. ( refer Minutes of meeting no 2 )

The contractor required to comply in the second proposal with 2 weeks from the date of issuance of NCR.